UPDATES!!!

The Asphalt Work has been delayed:

  • Schedule is TBD

The West Side of Nowland Court dates have changed:

  • You can not use your driveway until 10/14/2021

  • Thursday, 10/7/21 - new concrete curbs and gutters was poured

  • Wednesday, 10/6/21 curbs and gutters were removed

Nowland Court Construction Details - 9/20/21

As follow-up to an email that was sent in May, we are happy to let you know that the road repairs will begin on Nowland Court on Monday, 9/27/21, per the following schedule:

 

Week of 9/27/21 through 10/3/21: East Side of Nowland Court

  • During this week, cars can only be parked on the west side of Nowland Court, so we are asking all homeowners on the west side to park all of your vehicles in your garage or driveway beginning Sunday, 9/26/21.  This will allow the homeowners on the east side to park their vehicles on the west side of the street during this construction week.

  • Sunday, 9/26/21- all vehicles in use by east side homeowners will need to be moved from their driveway or garage on Sunday evening to either the west side of Nowland Court or to Nowland Drive.

  • Monday, 9/27/21- curbs and gutters will be removed. 

  • Tuesday, 9/28/21- new concrete will be poured for the curbs and gutters.

  • You cannot use your driveway until construction barrels have been removed on or after Monday morning 10/4/21.

Week of 10/4/21 through 10/10/21: West Side of Nowland Court

  • During this week, cars can only be parked on the east side of Nowland Court, so we are asking all homeowners on the east side to park all of your vehicles in your garage or driveway beginning Sunday, 10/3/21.  This will allow the homeowners on the west side to park their vehicles on the east side of the street during this construction week.

  • Sunday, 10/3/21- all vehicles in use by west side homeowners will need to be moved from their driveway or garage on Sunday evening to either the east side of Nowland Court or to Nowland Drive.

  • Monday, 10/4/21- curbs and gutters will be removed.

  • Tuesday, 10/5/21- new concrete will be poured for the curbs and gutters.

  • You cannot use your driveway until construction barrels have been removed on or after Monday morning 10/11/21.

Weekdays of 10/11/21 and 10/12/21: All of Nowland Court

  • Monday, 10/11/21- the entire asphalt road will be milled and repaired, so no parking on the street is allowed.  You may also have trouble accessing your driveway during this process, so you may want to park on Nowland Drive.  Paving will begin on Tuesday morning, so you will need to move your vehicles to Nowland Drive on Monday evening.

  • Tuesday, 10/12/21- Nowland Court will be paved with hot melt asphalt.  Homeowners will not have access to Nowland Court all day on 10/12/21, until the paving is complete and the contractor has left the subdivision.  Please plan to park on Nowland Drive until later Tuesday evening.

In addition, please be aware of the following during this construction period:

  • The above schedules are "weather dependent", so dates may be extended if necessary.

  • Garbage days- if your side of the street recently had the curbs and gutters poured with new concrete, you may want to consider placing your garbage on the opposite side of the street.  If so, please touch base with your neighbor across the street.

  • School bus routes may be affected, as buses may not be able to drive through the court.  Please make arrangements with your bus driver ahead of time for the duration of the construction project.

  • Mail delivery could be delayed on the days that work is being done.

  • Homeowners should not park along Palmer Road.

  • If you have low tree branches hanging over the road, you may want to trim them prior to 9/27/21.

  • Sprinkler systems should be turned off during the entire construction period.

Download document:

Nowland_Court_Construction_Flyer_210920.JPG